Construction Central Update – July 7, 2017

July 7, 2017 Construction Update: The summer construction season is in full swing as Larson Construction and 7 sub-contractors have been busy during Phase I of construction. Phase I includes construction includes a cafeteria, science wing, band and choir rooms (located in the NW corner of the Concert Hall) a varsity locker room & concessions (located on the southeast corner of the high school) addition.

Also part of the summer construction is the addition of 8 tennis courts and approximately 80 additional parking spaces.

Below is an update on Phase I construction projects.

CAFETERIA

  • Site prep work is well underway as 100 truck loads of dirt have been moved so far.
New Cafeteria


SCIENCE WING

  • Excavation and site prep work
Science Wing Addition


BAND-CHOIR ADDITIONS

  • Footings are 75% complete
  • Foundations are being poured
  • Masons will start to lay blocks for walls
Band and Choir Additions


LOCKER/CONCESSIONS ADDITION

  • Footings and the foundation work has started
Locker Room and Concessions Addition


TENNIS COURTS & ADDITIONAL PARKING

  • Fencing is being installed
  • Asphalt has been poured and set
  • Parking spaces have been painted

HIGH SCHOOL INTERIOR

  • New plumbing for hot and cold water is being installed this summer to prepare for the new additions
Interior Plumbing Work at the High School

June 6, 2017 Science-Band-Choir-Locker Room Update

JUNE 6, 2017 SCIENCE-BAND-CHOIR- LOCKER ROOM UPDATE: Phase I of the high school construction project is underway. Construction has begun on a a new science wing, band and choir classrooms (located in the NW corner of the Concert Hall) and a varsity locker room & concessions  (located on the southeast corner of the high school) addition.

Science  Wing Addition
Band and Choir Addition
Locker Room & Concessions Addition